Confederacion Hidrografica Meeting December 1, 2009.
As a result of a number of various breaches of planning consents and regulations by Camposol developer Groupo Masa the Mazarron administration decided that rather than resorting to more drastic solutions the most sensible and practical answer would be to revise the Plan Parcel. One of the most serious and significant transgressions was the illegal construction of a large number of properties over an existing rambia on sector D before notifying or obtaining the required authorization from the Confederacion Hidrografica. As an intended alternative to performing the functions of the original rambla Masa decided themselves to install three pipes and when details of this action were finally submitted to the Confederacion Hidrografica it was rejected as unsuitable and furthermore for failing to follow the correct procedures the developer incurred an undisclosed fine. Subsequently. As instructed Masa did submit a revised scheme which it is believed to have followed the Confederacion Hidrografica suggestion of an open artificial rambla circumventing the south western boundary of sector D. However, apparently this amended design was also turned down by reason of both insufficient information and the absence of geological and environmental impact reports.
Originally it had been hoped that the signing off of the revised Plan Parcel could have been completed in 2008 but especially being aware of the problems associated with the Confederacion Hidrografica acceptance of Masa’s proposals for the new rambla the CRA requested an update from the Mayor at last month’s Town Hall meeting. In reply the Mayor stated that further progression of the artificial rambla situation was now dependent on the environmental impact report being obtained from Masa and led us to assume that this might be the final hurdle to overcome. (A copy of the relevant question and answer from the Mayor is printed below)
Due to the importance surrounding this matter the CRA decided that further clarification was needed and so a meeting was arranged for December 1st with Snr Francisco Lopez at the Confederacion Hidrografica offices in Murcia. Although Snr Lopez proved to be most responsive to the questions put to him, the answers he gave did not give much hope that a speedy solution would be found. Also revealed was that it was not only just a matter of Masa producing the environmental impact report but along with the geological report the revised design for the project was still outstanding. Snr Lopez was asked that if in the event that Masa do not comply with those requirements what would then happen and although he was not in a position to advise on any timescales he was able to confirm that a failure to respond will result in the issuing of a denuncia against the company and of course the final outcome of any such action will be to a large extent reliant on Masa’s financial position. Also it was emphasised by Snr Lopiz that the whole procedure connected with this matter must be carried out through Mazzaron council channels.
Bearing in mind that the construction of this alternative rambla has serious ongoing consequences, included that related to final acceptance of Camposol and the issuing of Escrituras, the CRA will therefore be looking to arrange an urgent meeting with the Mayor as early as possible in the new year.
4. Could we please have an update on the signing off of the revised Plan Parcial for B, C & D Sectors & have the Confederacion Hidrografica been in contact with the Council?
A : The Mayor stated that this was a major concern for him and the Council. When they came to power the previous administration had allowed much work to be undertaken by Masa different to the original Plan Parcial for Sectors B, C & D. This included a bridge in the wrong place, many polygonos with more or less houses than approved and a problem caused by the building of houses on the rambla on Sector D. They had decided with the help of Masa to produce a revised Plan Parcial and this was completed in late summer 2008 and sent to the Confederacion Hidrografica in Murcia for approval. Part of the plan to resolve the rambla problem was for an artificial rambla to be constructed around D Sector. The Council have been chasing the Confederacion for some months to get the plan signed off but in a meeting between the two in September of this year the Confederacion Hidrografica has now requested an environmental impact report from Masa in relation to the planned construction of the artificial rambla. Everyone is now awaiting this report before any headway can be made on this issue.
GG stated that this situation was causing major problems for the homeowners of Sectors B, C & D who now find themselves in a position of having no or incomplete escrituras and no Certificates of Habitacion. Without these documents it is virtually impossible to sell their houses and in some cases this has caused severe financial hardship.